In the 2025/26 Noosa MP survey, 51% of respondents were undecided or wanted more information in relation to questions regarding energy and water including the Borumba Pumped Hydro Project, located 50 km southwest of Noosa near Imbil.
Anything that happens upstream in our catchment has an impact on our communities, hence projects such as this are important.
What is Borumba Pumped Hydro?
Pumped-storage hydroelectricity (PSH) or pumped hydro energy storage (PHES) is a large-scale energy storage system that functions like a giant water battery.
When electricity demand is low or when surplus energy is available from renewable sources like solar and wind, water is pumped from a lower reservoir up to a higher-elevation reservoir. This stores energy as gravitational potential energy and when power is needed, it is released back down through turbines to generate electricity.
The proposed project, last estimated in December 2024 to cost $18.4 billion, is designed to deliver 2,000 MW for up to 24 hours, which according to Queensland Hydro is equivalent to support 640,000 households at peak demand for four hours. It would involve:
– a new upper reservoir formed by six new dams
– a new, higher dam wall downstream of the existing Borumba Dam, increasing Lake Borumba’s storage capacity from 46 GL to 224 GL
– an underground power station connected by tunnels
Lake Borumba is an existing Seqwater dam that supplies water for irrigation and drinking water along the Mary River for towns including Imbil, Gympie, Noosa and Tiaro. Allocations from Lake Borumba also supply the SEQ Water Grid via the Northern Pipeline Interconnector.
Hence any changes at Borumba could affect the river system downstream, and all who rely on it.
More information on the project is available at Borumba Pumped Hydro Project | Queensland Hydro
Why is power storage needed ?
A growing share of Queensland’s electricity comes from rooftop and large-scale solar and from wind, and output from these sources varies with the weather and time of day. Storage allows surplus energy to be saved and used later.
The Queensland Government’s Energy Roadmap, released in October 2025, reports storage is essential to firm up variable renewable energy and to manage periods of very low daytime demand on the grid.
The Roadmap projects at least 3.1 GW of short-duration batteries by 2030, and an additional 1.6 to 3.4 GW of medium-duration storage by 2035 to be able to support the electricity grid as more solar and wind are added.
It also confirms coal and gas will continue to play a role in maintaining reliability in the near term.
Batteries generally store energy for a few hours where long-duration storage such as pumped hydro can supply power for longer periods, such as overnight or during extended spells of low solar and wind output.
Coal-fired generation is also changing. In October 2025, the owners of Gladstone Power Station, Queensland’s largest coal-fired power station, which began operating in 1976, notified the Australian Energy Market Operator that it could retire in March 2029, when its current supply contracts expire. The owners have said no final decision has been made and that the station’s life could be extended.
In 2026, the Queensland Investment Corporation (QIC) completed an assessment of four proposed pumped hydro projects on behalf of the State Government. QIC has stated that the assessment found a system need for pumped hydro from the mid-2030s,but has not published what that need is or how it was determined. For broader context, the Australian Energy Market Operator (AEMO)’s national plan forecasts electricity use to nearly double by 2050. QIC is now undertaking further assessment of Borumba and Capricornia (near Mackay) which it says considers broader benefits including system reliability and resilience, value for money for the State, and water security outcomes for communities, agriculture and other industry. The findings and assessment report are unavailable for public review with more information available at Pumped Hydro Energy Storage
Queensland Hydro now describes Borumba as a joint energy and water security project. What this means in practice, such as whether the enlarged Lake Borumba would provide additional water allocations, has not yet been made public.
Is it the right solution?
In April 2025, the Government said it had committed to progressing smaller, more manageable pumped hydro projects, and its Energy Roadmap assigned QIC to assess Borumba alongside smaller proposals. Some energy analysts have questioned whether 24-hour storage at this scale is needed, compared with batteries and smaller projects. The Mary River Catchment Coordinating Committee (MRCCC) has raised significant environmental concerns that under the current design, large volumes of water would be pumped between the upper reservoir and Lake Borumba on a daily cycle, causing significant fluctuations in water levels. It says this would keep fine sediment in suspension and send it downstream, and that the enlarged lake would flood breeding habitat for threatened species, including the critically endangered Mary River turtle, the endangered Mary River cod and the vulnerable Australian lungfish.
Impacts on these species were the main reason the Traveston Crossing Dam was refused federal approval in 2009.
Where is the project at now?
In December 2025, the Federal Government granted environmental approval for exploratory works only. These include geotechnical investigations, environmental studies and road upgrades. Main construction works have not commenced and would require separate state and federal approvals and a Government decision.
In June 2026, we asked the Treasurer for an update on QIC’s review, which was due mid-2026, and how the business case would be made available. The Treasurer’s office advised that:
“In its role as investment manager of Queensland Hydro, QIC is overseeing an in-depth analysis of the Borumba PHES and development of a revised Business Case. This is being undertaken in parallel with QIC’s Coordinated PHES Review to assess smaller, more manageable PHES projects including Borumba, Mt Rawdon, Capricornia and Cressbrook. More information on the QIC process and Borumba will be available in the coming weeks.”
In July 2026, QIC confirmed it had completed its assessment of the four proposed projects (Borumba, Capricornia, Mt Rawdon and Big T). In line with the 2026–27 State Budget, QIC is now undertaking further assessment of Borumba and Capricornia. To our knowledge, the revised business case for Borumba has not been made public.
Advocacy
Sandy has raised the MRCCC’s concerns with the Government, including directly with the Treasurer, asking they consider the MRCCC’s alternative and to engage with the MRCCC directly.
In MRCCC’s submission to Queensland Hydro’s 2025 consultation on the exploratory works, it called for two new reservoirs that operate independently of Lake Borumba and Yabba Creek, purely for generating electricity. If the project proceeds as currently proposed, the MRCCC has said it will continue to advocate for a new, purpose-built off-stream lower reservoir of approximately 72 GL on Borumba Creek (its “Borumba Creek balancing storage” proposal), so that water is pumped between the two new reservoirs rather than back and forth through Lake Borumba. It says this would allow a much smaller raising of the existing dam (about 10 metres instead of 20 metres) and reduce impacts on water quality, recreation and downstream water supply.
With Borumba now described as a water security project as well as an energy project, it is important that the revised business case is released so that communities can understand what is proposed, the costs and benefits, and what it means for the Mary River catchment and water supply. We will continue to seek its release, and update to 360.

Further information
Queensland Hydro’s Borumba Project Engagement Team can be contacted on 1800 433 939 or via borumba@qldhydro.com.au. Project updates and works notifications are available at www.qldhydro.com.au/projects/borumba.
For our previous Noosa 360 updates on water in our catchment, please visit https://sandybolton.com/?s=dam. We would appreciate any feedback from Noosa state electorate residents to inform our advocacy via noosa@parliament.qld.gov.au.